ACIS Instrument Support - Monthly Progress Report for March 2009 1. ACIS Characterization 1.1 Characterize and model radiation damage in ACIS CCDs ... Continued work on irradiation/annealing tests done at GSFC in 2005. Finalizing analysis. ... Provided calibration for BI CCD temperature-dependent CTI correction to CXC SOT. 1.3 Monitor scientific on-orbit performance of ACIS ... Continued monitoring of ACIS CTI, gain, trailing pixel pulseheight, detector efficiency, corner pixel distribution, spectral line centroid and width, and focal plane temperature. Updated monitoring web pages. (http://space.mit.edu/~cgrant/monitor.html) ... Updated web page which displays raw raw frame to include most recent data. (http://space.mit.edu/~fergason/acis/raw.html) ... Developed serial trailing monitoring for BI CCDs. Will post to web in April. ... Examining the use of Al-K line to calibration contamination instead of the much weaker L-complex. Some issues with systematics in fitting, probably due to changing background levels. Ongoing. 2. Engineering 2.1 Instrument hardware engineering performance ... Continue to monitor long term ACIS instrument performance. ACIS engineering continues to report nominal operations. ... Conducted two long (125 & 130 ksec) focal plane cooling tests. Focal plane temperature dropped quickly and was regulating at -125C (the set point). The spacecraft was in a favorable geometry with no Earth visible to the ACIS radiator. 2.2 Flight software maintenance 2.3 Instrument science performance ... Presented ACIS SI team report at the Chandra Quarterly. Provided focal plane temperature data to SOT for their presentation. ... Participated in monthly ACIS operations meetings. Discussed plan to reduce radiation belt backoff time from 6 to 5hrs from perigee and most recent focal plane cooling test. ... Participated in radiation working group telecon discussing the radiation environment during perigee as the Chandra orbit changes. ... Participated in meeting to update the MIT ACIS instrument team on changes in EPHIN performance, required time for ECS measurements, and possible changes in radiation belt timing. ... Reviewed new parameter blocks for ACIS CTI observations which use an alternate set of CCDs (I0-I3,S1,I3). Will be used regularly starting in April. ... Continued daily quick-look processing of ACIS telemetry and maintained Web interface to ACIS real-time data. ... Continued to publish the "annotated DOT" timeline reports. 3. CXC Support 3.1 Provide user support ... Updated ACIS memo listing calibration ObsIDs and observation characteristics (ACIS Memo #165). 3.2 Provide data analysis support ... Participated in CXC Cal/Ops modeling discussion group. Discussed updates to contamination calibration and ECS observation strategy. ... Continued to maintain ACIS calibration database of ground and flight data products. 4. OCC Support 4.1 Use of MIT/ACIS EGSE at OCC ... Continued support and maintenance of ACIS EGSE software and hardware at the OCC. Replaced malfunctioning tape drive. ... Continued work on improving configuration management of the ACIS workstations in the TST area of the Chandra OCC. Work nearly complete. Outreach: none this month all recent memos available at http://space.mit.edu/ACIS/iacis.html